Work
on site started in early November 2007 with the clearing and
removal of existing buildings and trees. Then the erection
of billboards and hoarding was carried out before the land
survey. Moving in of piling machines started in early December
2007 and the progress has been satisfactory as shown in the
photographs taken of the site progress from 07-11-07 until
27-12-07.
Site
progress work
21 to 27 Dec 2007
Coring
machine on site
Joining
of casing
Pouring
of ready mixed for bore pile
Pouring
of ready mixed
for bore pile
Removing
of casing
Removing
of casing
Removing
of casing
Removing
of casing
Preparing
for load test for
1st piling
Preparing
for load test for
1st piling
Site
progress work
11 to 19 Dec 2007
Core
of 1st pile
Core
of 1st pile
Equipments
& machineries moving in for bore pile
Hoarding
& billboard erectioning
Equipments
& machineries moving in for bore pile
Land
survey & pegging
Surveying
& identifying the positions for bore pile